Quantitative Aptitude, Time and work

A and B working separately can do a piece of work in 9 and 12 days respectively. If they work for a day alternatively, A beginning, in how many days, the work will be completed?

  • Seshathri
  • 29 अप्रैल
  • 2426 दृश्य
  • 1 उत्तर
Your Answer

10 1/4 Days.. Please reply if It's Wrong

1
  • Could you please explain me ur answer.

  • Great Shrijith!! You are obviously right.

aptitude
मॉक परीक्षण अभ्यास के लिए
aptitude